Award of Large-scale Port Construction Project in Bangladesh
Tokyo, Japan - March 07, 2025 - A joint venture of Penta-Ocean Construction Co., Ltd. (hereinafter POC, President Takuzo Shimizu) and TOA Corporation (President Takeshi Hayakawa) has recently been awarded a construction contract from the Chittagong Port Authority of Bangladesh for the “Matarbari Port Development Project Phase-1 Package 1: Procurement of Civil Works for Port Construction”. The contract amount is approximately JPY 73.4 billion, and the construction period is 42 months.
The project is financed through a yen loan provided by the Japan International Cooperation Agency (JICA), involving the construction of a container and multipurpose terminal in the Matarbari area, Cox’s Bazar District, Chittagong Division. The main scope of the project encompasses the construction of a jetty (extension 760m, 16m deep), reclamation, soil improvement, paving work for the yard (36ha), construction of buildings such as administration building, and various terminal facilities.
The container and multipurpose terminal will be located within the port constructed by POC as the port and land development work for the “Matarbari Ultra Super Critical Coal-fired Power Project” (awarded in 2017), and the terminal will utilize the same navigation channel constructed then.
In parallel with its robust GDP growth, Bangladesh’s container cargo demand is expected to surge. However, the Chittagong Port, which handles 98% of all container cargo, has only 9.5m depth, and this necessitates the development of a new port that can accommodate the recent increase in the size of international ships and future cargo demand. As the first deep-sea port in Bangladesh, the Matarbari Port is supposed to handle up to 8,000 TEU-type container ships. This is expected to alleviate chronic congestion at the Chittagong Port, streamline logistics operations with the neighboring countries, and thereby accelerate the economic growth in Bangladesh.
Over the past several decades, POC and TOA Corporation have been involved in numerous overseas construction projects, including port construction projects financed by Official Development Assistance (ODA), civil engineering or building construction projects for state and local governments such as the government of Singapore, as well as private civil engineering or building construction projects. Going forward, POC and TOA Corporation are committed to contribute to the further development of Bangladesh by leveraging the wealth of experience and technological capabilities accumulated both in Japan and overseas.
Project site

Project outline
Project Name | Matarbari Port Development Project Phase-1 Package 1 Procurement of Civil Works for Port Construction |
---|---|
Client | Chittagong Port Authority |
Contractors | Penta-Ocean Construction Co., Ltd. (65%) TOA Corporation (35%) |
Contract amount | JV total: Approximately JPY 73.4 billion |
Project site | Matarbari area, Cox’s Bazar District, Chittagong Division, People’s Republic of Bangladesh |
Construction period | 42 months |
Main project scope | Container/multipurpose jetty: L=760m Tugboat wharf: L=382m Dredging: 7,200,000m3 Yard reclamation: 36ha Soil improvement: -By Cement Deep Mixing Method: 495,000m3 -By Consolidation Acceleration Method: 356,000m2 Paving work: 33ha Construction of administration buildings, gates, workshop etc.: 21 nos. Terminal facility construction: 1 lump sum |